Construction of a commercial milk processing and bottling plant on Withybush Industrial Estate.
DKAN Groundworks contracted works included all groundworks activities on the greenfield site. Cut and fill works were completed during a challenging wet winter, requiring excess water management. Construction of foundations, drainage and concrete slabs, highway and loading bay construction and all finished grading of landscaped areas.
Drainage consisted of specialist stainless steel and fusion welded polypropylene systems, alongside standard foul and stormwater drainage.
Concreting included mass fill foundations, structural concrete to retaining walls and silo bases, power float finish to floor slabs and kerbing.
Client: Pembrokeshire Creamery Ltd
Principal Contractor: Pembrokeshire Creamery Ltd
Start Date: October 2022
Duration: 52 weeks
Groundworks Contract Value: £4 million