Njord Ltd were installing a wind farm at Bryn Blaen and DKAN Groundworks were contracted to excavate trenches for just over 15km of high voltage cables (cables to be laid / pulled by the power company). A trenching machine was utilised for a percentage of the works which involved excavation in and alongside the main A470 highway and across remote rural landscapes. Ducts were laid where necessary.
Client: Njord Energy
Principal Contractor: Neath Ltd
Start Date: September 2017
Duration: 24 Weeks
Groundworks Contract Value: £25k